RoomScene 3D
Download

Rack capacity planning for broadcast equipment rooms

Whether the next server fits is four questions, not one: is there a contiguous block of U, is there power on both feeds, can the rack and floor take the weight, and can the room cool it. This article works through each with numbers.

Published

Four limits on every rack

A rack runs out of one thing before the others. In a CAR full of 1U converters it is usually space. In a rack of playout servers and encoders it is power. In a rack with a UPS and battery cabinets it is weight. Capacity planning means tracking all four and knowing which one binds for each rack.

  • Space: rack units of mounting height.
  • Power: what the rack's feeds can deliver, with redundancy.
  • Weight: what the rack frame and the floor under it can carry.
  • Cooling: what the room can remove. Every watt that goes into a rack comes out as heat.

Space: total free U is not the number you need

A rack unit (U) is 1.75 inches, 44.45 mm, of vertical mounting space. Broadcast racks are almost always 19-inch: the equipment panel is 19 inches (482.6 mm) wide and the rails are drilled with three holes per U. A 42U rack has 42 × 44.45 mm, about 1.87 m, of mounting height. Depth varies far more than height, so check it: a long server does not fit a shallow audio rack, whatever the U count says.

The figure people quote is total free U. The figure that matters is the largest contiguous free block, because a device needs adjacent U. An example rack:

A07 (42U)    used 30U    free 12U
free blocks: U41-42 (2)  U33-35 (3)  U17-20 (4)  U9 (1)  U1-2 (2)
largest contiguous block: 4U

a 2U server fits     a 4U frame fits     a 5U frame does not

Twelve free U, and a 5U router frame still needs another rack. Free space scatters over years: a device is removed, a blanking panel goes in, nobody consolidates. Track both numbers per rack, and when you plan a move, look at whether shifting two or three 1U devices would open a useful block.

Power: nameplate, measured and the budget

There are three power figures for every rack, and mixing them up causes most surprises.

  • Nameplate: the rating printed on the device or its power supply. It is a ceiling, not a forecast. Real draw is usually well below it. A server with two redundant 750 W supplies has a nameplate of 750 W, not 1,500 W: the second supply is there to take over, not to add.
  • Measured: what the PDU or the device reports. It changes with load. A playout server encoding several channels draws more than the same server idle. Measure at the busy hour, during a live event with every channel on air, not on a quiet Sunday morning.
  • Budget: what the rack is allowed to draw, set by its feeds and by the cooling in that part of the room.

Planning against the sum of nameplates is safe and wastes capacity. Planning against average measured draw is efficient and will trip a breaker one day. A common middle path is measured peak plus headroom, with nameplate used for new devices until they have been measured. Whichever you choose, write the rule down so every planner uses the same one.

A/B feeds: each feed must carry the whole rack

Racks with dual-corded equipment usually have two PDUs on separate feeds, A and B. In normal operation the load shares between them, roughly half each. The point of having two is that when one fails, the other carries everything. So the rule is: the whole rack load must fit within the capacity of one feed.

A worked example, with example figures. Each feed is a single-phase 16 A circuit at 230 V:

StepFigure (example)
Feed rating16 A × 230 V = 3,680 VA
Continuous-load margin of 80 %2,944 VA
At a power factor of about 0.95about 2.8 kW per feed
Rack power budget with A/B redundancy2.8 kW, not 5.6 kW
Measured now: feed A / feed B1.25 kW / 1.15 kW = 2.4 kW total
If feed B fails, feed A carries2.4 kW, 86 % of 2.8 kW

The 80 % margin follows North American electrical code for continuous loads on standard breakers, and many sites elsewhere use the same margin as practice; check the rule that applies to your installation. With 32 A feeds the same arithmetic gives about 5.6 kW per rack.

Two traps. Single-corded devices, an old frame or a small converter, sit on one feed only and go down with it; either give them an automatic transfer switch or accept the risk knowingly. And a rack where feed A shows 1.9 kW and feed B 0.5 kW is not balanced. It usually means single-corded gear is concentrated on A, or both supplies of some servers are plugged into the same PDU. Either way, part of the redundancy exists only on paper.

Weight and cooling

Every rack has a static load rating from its manufacturer. It covers equipment mounted correctly on the rails, often with a lower figure if the rack is on castors rather than levelling feet. Heavy items go low: UPS units, battery packs and large frames at the bottom keep the centre of gravity down.

Then there is the floor. A raised floor tile, or a slab in an old building, has its own limit, and a full rack concentrates its weight on a small footprint. As an example, a 600 × 1,000 mm rack carrying 600 kg of equipment puts about 1,000 kg per square metre on the floor, before the rack's own weight. A rack of batteries on a raised floor is a question for the building engineer.

Cooling closes the list. Power in is heat out: 1 kW of load is about 3,412 BTU/h that the CRAC units must remove. Watch inlet temperature rather than room temperature; the widely used ASHRAE recommended range for equipment inlet air is 18 to 27 °C. A rack that is fine on power can still be the one that runs hot because it sits at the end of a row, far from the cold air.

Worked example: where does the new encoder go

A new 2U encoder is coming: 450 W planning figure, 18 kg. Three racks in the CAR are candidates. All figures are examples; budgets are 2.8 kW per rack as above, load limits 800 kg.

RackFree U / largest blockPower nowPower afterWeight afterResult
A066 / 22.10 kW (75 %)2.55 kW (91 %)538 kgFits, rack goes yellow
A0712 / 42.40 kW (86 %)2.85 kW (102 %)428 kgSpace yes, power no
A0818 / 101.20 kW (43 %)1.65 kW (59 %)318 kgFits, best balanced

A07 has the most obvious free space and is the wrong answer: one feed failure would leave it over budget. A06 works but leaves no headroom for the next device. A08 is the choice, and it also leaves the 4U block in A07 free for a frame that needs it.

Capacity in RoomScene 3D

RoomScene 3D keeps these figures per rack and rolls them up per room and per site: used and free U, the largest free block, nameplate power against the rack's power budget, and weight against its load limit.

  • Measured power and temperature are read from Zabbix every two minutes: PDU totals, or the sum of the phases, in W or kW, and inlet and ambient sensors in °C. Where a rack has no PDU, its power is the sum of its devices' own readings.
  • A/B feeds are shown per PDU, so you can see whether one feed could carry the rack alone.
  • At 80 % of the budget a rack turns yellow, at 100 % red. Heat maps in 3D show U usage, power, weight or inlet temperature across a row.
  • “What fits where” does the table above for you: enter height in U, power in W, weight in kg and quantity, and get the racks that can take it, best balanced first. You can drop the device into a draft from there.
  • With a draft open, the capacity page shows “now” and “after the draft” side by side. A draft that goes over budget is flagged, not blocked; the approver sees the warning.

How those warnings travel through an approval is covered in planning an equipment move. The capacity view sits next to the rack elevations, and the DCIM comparison explains where RoomScene 3D stops: it reads PDU power from Zabbix and does not model the power chain down to the breaker. The 30-day trial has every feature on; download it and check the numbers against one of your own racks.

Try it on your own rooms

RoomScene 3D is a 30-day trial with every feature on. Install it on a test server and import one room.

Download the 30-day trial Ask for a quote

contact@roomscene3d.com · tahirfeyzioglu@gmail.com